JCB - Case Study
st1\:*{behavior:url(#ieooui) }
Background
JCB are
one of the world’s top three manufacturers of construction equipment, employing
over 8,000 people in factories spread across four continents and with
operations in over 150 countries. In the UK their name has become synonymous
with engineering vehicles as a whole, to the point that the term can be found
in the Oxford English Dictionary.
Problem
Like any company, JCB spends
a lot of money each year on marketing. A part of this marketing involves computer-rendered digital images of various
JCB designs, created using LightWave 3D graphics program. However, JCB had only one computer on-site
dedicated to rendering the images and this was also being used by the 3D
designer for other purposes. The result was that image rendering would take several
days, even a week, during which time the computer could not be used for
anything else. Because of this it was
becoming increasingly difficult to maintain a sufficient work rate and to
meet deadlines.
What was needed was a
solution that could achieve the following:
- Reduced rendering times to speed up turnover of
images.
- The ability to be working on a machine while the
rendering is occurring in the background.
- Maximum potential and minimum disturbance to the
rest of the network through its own dedicated
computers.
- Adherence to JCB’s existing security policies.
Solution
JCB consulted with Jigsaw
about the best solution. Installing a render
farm would provide the answer to JCB’s problems and various options were
looked at before a decision was reached. It was decided that the best option
was to install a Muster render farm
with an edit station and six Xserve servers as render nodes, alongside
six more nodes on Mac Pros that JCB already had and wished to use. During
pre-installation testing Muster was found to be incompatible with the Mac-based
Lightwave software so the render farm was switched to Screamernet instead.
This solution met all the
requirements JCB had for the new system, offering a significant performance
increase at a price within their budget.
Implementation
JCB already had some of the
required equipment on-site, including the six Mac Pros and a rack mount for the
servers. The rest of the equipment was delivered first to Jigsaw, where much of
the set-up work on the Xserve servers and edit station was done before it was
transported to the site for installation, thus
speeding up the actual time needed on-site and minimising disruption caused by
the installations.
It is also at this time that
checks are run to ensure the equipment works and that the software is
functioning and compatible. This allows unexpected problems to be spotted
before installation has been completed and therefore makes corrections smoother
and quicker.
The on-site installation itself took only two days, partly because JCB
was able to set up the Mac Pros and install the necessary security software
beforehand, preparing the way for the Jigsaw engineers.
Benefits
There were two primary
benefits as a result. Primarily, the render farm means a lot more processing
power is available to be used for rendering the designs, meaning shorter rendering times and higher quality. In addition,
the presence of dedicated servers instead of a single overworked CPU means
designers will no longer suffer from the downtime brought about while an image
was being rendered, when they were previously unable to use their computer.
Beyond these, though, the
decision to also install six Mac Pros as additional nodes allows for even greater processing power to be drawn
upon when necessary by shifting these nodes to work with the servers. This can
also easily be done during evenings and weekends when they would otherwise be
idle. Finally these Mac Pros mean greater
access to the rendering system, as now more than one workstation is
connected to the rendering data and hardware.
Summary
JCB required a means to more
efficiently render their digital design images and enhance their effectiveness
through the use of a dedicated rendering system. Jigsaw was able to provide
this through the installation of a full render farm with dedicated servers,
providing them with a new system that met their requirements for performance
and functionality while not exceeding their budget.
The possibility of upgrades
to the render farm in the future remains, with changes from simple software
upgrades to the expansion of the hardware itself (such as the addition of
further servers to boost the power of the render farm) all being viable.
Deciding on the exact render
farm for your needs isn’t a simple ‘compare the numbers’ exercise. It’s more
often a matter of looking at the individual requirements and getting expert
technical help for that particular case. One possible starting point is on the
Jigsaw website itself – several articles on render farms can be found at http://www.jigsaw3d.com/render-farms.aspx.
Get in touch if you have any questions about your 3D workflow - call 03332 409 309 or email 3D@jigsaw24.com